Dog Kennels x
Reconstruction Iraqi Army building Has been damaged after the liberation of Iraq.
Project Details
- Beneficiary side: USA Army
- Prime contractor: KBR
- Subcontractor: Al-Mubarak International Group
- Location: Green Zone Area – Baghdad – IRAQ
- Date of Start: 13/01/2005
- Reasons for Delay: Change order to update the scope of work by the client
- Subcontract No: 02H8-US-SJ00048
- Project manager: H. Mubarak
- Contract value: $846,395.00
- Date of Completion: 13/06/2005
- Problems at Place of Work: None
The Target of the Project
- The reinvention and construction of the old building and adding a new building to become two:
- The first building for dog kennels.
- The second building for dog trainers’ service facilities.
Achievements
- Completed all construction building, electrical works, and mechanical works without the need for the prime contractor or assistance from other subcontractors.
- Relied on in-house company staff due to the security implementations of the Green Zone.
- Followed and implemented all security regulations, HS & QC standards to complete the project within the 120-day deadline.
Work Stages
A. Civil Works
- Demolishing of the damaged building.
- Design and drawings.
- Surveys, leveling site, and grading.