Al AASAM Building, Baghdad, Iraq
contact@mubarakint.com
+964 780 195 6006

Main Maintenance facility parking

Main Maintenance facility parking x

Project Details

  • The Target of the Project:
    • Provide foundation for two-part concrete paving:
      1. Part One:
        • Preparation of soil.
        • Provide, grade, and compact sub-base installation.
        • Concrete paving with 8-inch (20 cm) 4000 psi compressive strength concrete slab.
        • Approximate area: 53,170 sqft (4,949 sqm).
        • Two layers of reinforcing steel.
      2. Part Two:
        • Pouring 6-inch (15 cm) 3500 psi concrete slab.
        • Approximate area: 20,350 sqft (1,891 sqm).
        • Designed concrete structure.
        • Provide and install 3 sliding doors at the entrance.
  • Prime contractor: KBR
  • Subcontract No: 02H8-US-SJ00263
  • Contract value: $329,000.00
  • Date of completion: 25/11/2005
  • Beneficiary side: USA Army
  • Subcontractor: Al-Mubarak International Group
  • Location: International Zone Area – Baghdad – IRAQ
  • Date of Start: 01/10/2005
  • Duration: 55 days

Work Details

  • Civil Works:
    • Site preparations.
    • Leveling of the site.
    • Concrete foundation.
    • Steel reinforcement work.
    • Applying crushed stones on the floors.
  • Mechanical Works:
    • Supply and install 3 sliding doors (6 m each).